A clash found on screen costs minutes to fix. The same clash found on site, a duct running straight through a beam, can cost days of rework, a revised drawing and an unhappy client. MEP clash detection exists to move those discoveries from the site to the model.
What a federated model is
Each discipline (architecture, structure, mechanical, electrical, plumbing) usually works in its own model. A federated model combines them into one shared view for review, typically in a tool such as Navisworks or a cloud coordination platform.
Federation does not merge ownership. Each discipline still edits its own model; the federated view is where everyone checks how they fit together.
The three types of clashes
Hard clashes
Two elements physically occupy the same space, such as a pipe through a column or a duct through a beam. These are the obvious ones, and the most expensive if they reach site.
Soft (clearance) clashes
Nothing overlaps, but required space is violated: no room for insulation, maintenance access or code clearances around equipment.
Workflow (4D) clashes
The geometry is fine, but the construction sequence is not: equipment that cannot be installed because a wall goes up first, or a crane path blocked by temporary works.
How a coordination round works
- Collect the latest models. Every discipline publishes its current model on an agreed date.
- Check before you clash. Confirm shared coordinates, units and that each model is the current revision. Clash results from misaligned models are just noise.
- Run the clash tests. Run them by system pair (for example structure vs. ductwork) using agreed tolerances.
- Group and filter. One badly routed duct can create 200 clashes. Group them into real issues before anyone reads the report.
- Assign each issue. Every issue goes to one named discipline lead, often using BCF issues so it opens directly in their software.
- Resolve and retest. Designers fix the issue in their own model; the next round confirms it is closed.
Rules that keep clash reports useful
- Agree tolerances up front. A 5 mm overlap in a ceiling void may be acceptable; in a structural connection it is not.
- Set priorities. Structure and large ducts first, small pipes and cable trays later.
- One owner per issue. Issues shared between “everyone” are resolved by no one.
- Track status, not just counts. “Open, in progress, resolved, verified” tells you more than “312 clashes”.
- Keep design decisions with the designers. The coordinator finds and documents issues; the responsible engineer decides the fix.
What you should receive after each round
- A short issue list grouped by location and system, with screenshots
- Who owns each issue and the due date
- What was resolved since the last round
- Updated models or a note on which revision was checked